Integrated Development of Small and Medium Towns
 
 

I.D.S.M.T. AT A GLANCE
As on 31.03.07

    (Rs. in lakhs)
    Phase-I Phase-II
1. Total no. of towns covered 85 Nos 37 Nos
2. No of towns covered in 2005-2006 0 No. Nil
3.* Towns yet to be covered 1 No  
4. Total approved cost of projects 12125.95 16,958.81
5. Total Central Assistance received 5303.58 4712.03
6. Total Central Assistance passed over 5272.61 4514.80
7. Total State share released 3516.46 3106.75
8. Total amount passed over 8789.07 7621.55
9 Total Loan needed 2251.54 7229.70
10 Total FI Loan sanctioned 470.03 0.00
11 Total expenditure made 8854.82 5187.73
12 Assets created : nos  
  a) Markets / Commercial Complex 120  
  b) Roads 116  
  c) Bridge 3  
  d) Industrial Estate 15  
  e) Bus / Truck Terminal 35  
  f) Tourist Dormitories  50  
  g) Site & Service Schemes 30  
  h) Cattle Shed 3  
  i) Conversion of Service privies 22000  
  j) Community Latrines 70  
  k) Culverts 44  
  l) Others 40  
* Project proposal for the town of Panskura has been sent to TCPO/GOI for appraisal.
Objective:

  • To reduce the pressure of population on the city of Kolkata by making Integrated Development of Small and Medium Towns outside the Kolkata Municipal Area
  • To transform those towns as centre of development for providing additional scopes for employment
Covered Municipality: 4 municipalities out of the 85 municipalities outside the KMA areas (So far)

Covered ULBs: 2 ULBs of KMA (64 Urban Local Bodies have already been completed.)

Financial Assistance: Central Government (Rs.42.18) and State Government (Rs.31.72 crore) Amount of Rs.72.87 crore have been allotted to the above-mentioned no. of municipalities
 
Objective Implementation ULB wise fund release 2006-07
 
Development Programmes
 
 
 
 
 
 